Project Profile:
Community of Jesus Church
Project Summary
The Community of Jesus Church needed overflow parking but the city would not allow additional hard surface pavement. The church chose Grasspave2 for the beauty and strength.
Address
11 Bay View Dr., Orleans, MA 02653
Install Size
278 m2 (3000 sq ft)
Designer
Community of Jesus Church
Contractor
Installation done by the church congregation.
Project Gallery
Congregation members lay an additional section of Grasspave2 porous paver.
A congregation member snaps one roll of Grasspave2 porous pavement to a previously installed roll.
Sod is placed over the sand-filled section of Grasspave2 porous pavement.
Nearly completed, this parking lot is about 3000 sq ft (278 sq meters).
Congregation members roll sod on top of the sand-filled Grasspave2 rings.
The completed Grasspave2 parking lot with an additional storm collection drain.