Project Profile:
Gym 2000
Project Summary
Onsite stormwater - from the Gym 2000 site and adjacent Day Care building site - filters in through the vegetated swale and also enters through inlets in high volume cases. The required position of the detention system and the amount of stormwater containment needed made Rainstore3 the only choice in this situation. An above ground (open) detention pond was not used for safety reasons: children frequent the area.
Address
Castleton & Industrial Way, Castle Rock, CO
Install Size
378 cu meters to store 94,000 gallons (21 unit high cells )
Designer
Kevin Archer with David E. Archer Associates, Castle Rock, CO 303-688-4642
Contractor
MPC, 5400 W Jewell Ave, Ste 1A, Lakewood, CO - 303-934-6898
Project Gallery
After excavation is complete, workers put a layer of geogrid on the bottom of the area for stabilization.
The 21 unit high cell stacks are lifted into the hole.
An opening is left in the chamber for a maintenance port to be added later.
Some of the Rainstore3 cell are covered with the fabric as workers position the remaining cells.
Workers easily position the cells.