303-233-8383 [email protected]

Project Profile:

Shippensburg University, Shippen Hall

Project Summary

The newly seeded grass was taped off to prevent any pedestrian traffic from trodding on it.

Address

Shippensburg, PA 17257

Install Size

1450 m2 (15,608 sf)

Designer

N.A.

Contractor

Black Landscape

Project Gallery

A Turf-Reinforce Sustem was installed in the fire lane access areas at Shippensburg University in Shippensburg, Pennsylvania, using Grasspave2.
Shippen Hall - fire lane is behind this building and runs from one street near Dauphin Hall to Grace Luhrs University Elementary School.
Grid Pavers were installed in the fire lane access areas at Shippensburg University in Shippensburg, Pennsylvania, using Grasspave2.
Near Dauphin Hall the grass has just been seeded and the GP2 area is taped off, since the original GP2 was put in two years prior to this photo.
Grass Paving was installed in the fire lane areas at Shippensburg University in Shippensburg, Pennsylvania, using Grasspave2.
The other end of this long fire lane between two side walks is near the Grace Luhrs University Elementary School in the background on the right.
A Porous Fire Lane was installed in the fire lane access areas at Shippensburg University in Shippensburg, Pennsylvania, using Grasspave2.
Looking back along the full length of the GP2 fire lane, one can see that the new seeding is doing very well.